North Shore Wastewater Treatment Plant Project Two-week Look Ahead Schedule: August 23 – September 5, 2021

This two-week look ahead schedule highlights upcoming planned construction activities and work hours, including low impact nighttime work and anticipated noise levels.

Please note that work is weather dependent, and timelines are subject to change.

We don’t anticipate the activities scheduled over the next two weeks will generate noise beyond typical ambient noise levels, but we are continuing to monitor construction-related noise and will make adjustments as required.

Maintenance Holes and Bypass Construction

Per the notification issued on June 28, construction of two new maintenance holes required for North Shore Wastewater Treatment Plant Project pipe connections has started. The maintenance holes will be located in the West 1st Street laneway, just north of West 1st Street and east of Philip Avenue. Bypass pipe testing and commissioning is anticipated to take place during the week of August 22 and excavation and shoring of Maintenance Hole #1 will begin shortly thereafter.

Some noise and vibration impacts are anticipated for businesses in close proximity to this work and noise shielding, and vibration monitoring protocols have been put in place to mitigate related concerns. The construction of the new maintenance holes is anticipated to be complete in October 2021.

Nighttime Noise Enquiry Protocol 

To submit an enquiry related to Project construction noise during nighttime hours (8:00 p.m. to 7:00 a.m.):

  • Call the Community Liaison Officer phone number: 604-928-7810
  • Provide details about the noise being reported to Call Centre staff
  • The Call Centre will immediately share this information with the overnight site superintendent, who will investigate and take corrective action, as appropriate.
  • The Community Liaison Officer will follow up by email the following morning to confirm details and provide an update on the status of the enquiry.

Single Lane Alternating Traffic

In addition to the construction activities noted above, Single Lane Alternating Traffic will continue as and when required on West 1st Street, between Pemberton Avenue and Phillip Avenue, until mid-October. During the peak traffic periods of 6:00 a.m. to 9:00 a.m.; and 2:00 p.m. to 6:00 p.m., one lane of traffic in each direction will be reinstated.

If you have any questions about the work described in this notification, or would like to sign up for Project updates, please contact the Project’s Community Liaison Officer at 604-928-7810 or community@accionadbjv.ca.

Kind regards,Project TeamNorth Shore Wastewater Treatment Plant Project107 Pemberton Avenue
North Vancouver, BC V7P 0B9
Tel: 604 928 7810
Email: community@accionadbjv.ca
www.northshorewwtp.ca