North Shore Wastewater Treatment Plant Project Two-week Look Ahead Schedule

Thank you for your continued patience as work on West 1st Street and the treatment plant project site progresses.

We are introducing a regular project look-ahead schedule to keep you updated on what activities to expect over the next two weeks, particularly regarding possible construction noise.

The table below shows the planned construction activities from May 31 to June 13, 2021.

Please note that work is weather dependent, and timelines are subject to change.

We don’t anticipate the activities scheduled over the next two weeks will generate noise beyond typical ambient noise levels, but we are continuing to monitor construction-related noise and will make adjustments as required.

If you have any questions about the work described in this notification, or would like to sign up for Project updates, please contact the Project’s Community Liaison Officer at 604-928-7810 or community@accionadbjv.ca.

Kind regards,

Project Team North Shore Wastewater Treatment Plant Project