Project Activity Update

The following is an update on current Project activities:

  • Stone column installation is over 90% complete.
  • Pre-load (piles of gravel and aggregate material) activity is underway throughout the site. This work is required as part of ground improvements.
  • Construction of the hardened barrier wall on the west side of the site (closest to Philip Avenue) is now complete.
  • Regular Project hours resumed March 17. Work takes place 7:00 a.m. to 8:00 p.m. Monday to Friday, and 9:00 a.m. to 5:00 p.m. on Saturday.
  • The first edition of the Project’s community newsletter is available on our resources page. If you wish to sign up for email updates, please contact community@accionadbjv.ca.

Thank you for your continued interest in the Project. Please do not hesitate to contact our Community Liaison Officer at community@accionadbjv.ca should you have any questions.